UTSC Wireless Upgrade Project


Building Status

For the status of the wireless deployment in a specific building, please review the following table.

  • Complete: full wireless coverage in building.
  • In progress: building wireless coverage is currently being expanded.
  • Partial coverage: wireless coverage is available in select areas. Improvements to coverage are pending.
  • No coverage: no wireless coverage is currently available within this building.

Last updated December 01, 2023


UTSC Campus

Campus BuildingĀ Wi-Fi 5Planned Upgrade Wi-Fi 6
Service Date
Wi-Fi 6
Upgrade Status
Sam Ibrahim n/an/aMay 2024planned
Instructional CentreCompleteDecember 2022December 2022Complete
Bladen WingCompleteDecember 2022December 2022Complete
Science ResearchCompleteOctober 2022October 2022Complete
Student CentreCompleteOctober 2022October 2022Complete
Toronto Pan-Am Sports CentreCompleteOctober 2022October 2022Complete
Miller Lash HouseCompleteOctober 2022October 2022Complete
NCCompleteOctober 2022October 2022Complete
VLCompleteOctober 2022October 2022Complete
PortablesCompleteOctober 2022October 2022Complete
Valley ShopCompleteOctober 2022October 2022Complete
Humanities WingCompleteSeptember 2022September 2022Complete
Environmental Science & ChemistryCompleteAugust 2022August 2022Complete
Science WingCompleteAugust 2022August 2022Complete
ARCCompleteAugust 2022August 2022Complete
Residence 4CompleteAugust 2022August 2022Complete
Residence 1CompleteAugust 2022August 2022Complete
Residence 2CompleteJune 2022June 2022Complete
Residence 3CompleteMay 2022May 2022Complete
Arts & AdministrationCompleteJanuary 2022January 2022Complete
Social SciencesCompleteJanuary 2022January 2022Complete